Entergy's power system must be rebuilt, not just repaired, according to the company's CEO.
Renae Conley said Monday that both the Nelson and Sabine power stations are off-line as Entergy inspects those facilities.
She said that 117 transmission lines and 125 substations are out of service. She said she expects both numbers to climb.
"It will take weeks, not days, to restore power," she said.
Entergy spokesman Sheila Mott said that it may take three weeks or longer for some power to be restored.
"Many people will not see their power restored next week," Mott said.